최신 NETA CAETS NETA_2 무료샘플문제:
1. You arrive to perform acceptance testing on a newly installed indoor 15 kV switchgear lineup. Covers are removed and conductors are exposed with taped ends. What is thecorrect initial action?
A) Verify the source is de-energized and apply lockout
B) Assume the equipment is safe since it is new
C) Proceed with visual inspection only
D) Begin insulation resistance testing
2. OSHA requires testing of a voltmeterafterverifying absence of voltage when testing circuits above what voltage level?
A) 120 V
B) 240 V
C) 600 V
D) 50 V
3. A 120 VDC circuit draws0.83 amperes. How much power is consumed?
A) 100 W
B) 120 W
C) 145 W
D) 83 W
4. Sample valves should be flushed with at least how much waste liquid before collecting a transformer oil sample?
A) Until temperature stabilizes
B) One gallon
C) One quart
D) One pint
5. Duringprimary current injection testingof a low-voltage circuit breaker, the breaker trips instantaneously at
8× its long-time pickup setting, even though the instantaneous element is set to10×. What is the MOST likely cause?
A) Improper test lead placement
B) CT saturation
C) Incorrect short-time delay setting
D) Thermal memory enabled
질문과 대답:
| 질문 # 1 정답: A | 질문 # 2 정답: C | 질문 # 3 정답: C | 질문 # 4 정답: C | 질문 # 5 정답: B |














903 개 고객 리뷰
품질과 가치ITCertKR 의 높은 정확도를 보장하는 최고품질의 덤프는 IT인증시험에 대비하여 제작된것으로서 높은 적중율을 자랑하고 있습니다.
테스트 및 승인ITCertKR 의 덤프는 모두 엘리트한 전문가들이 실제시험문제를 분석하여 답을 작성한 만큼 시험문제의 적중률은 아주 높습니다.
쉽게 시험패스ITCertKR의 테스트 엔진을 사용하여 시험을 준비한다는것은 첫 번째 시도에서 인증시험 패스성공을 의미합니다.
주문하기전 체험ITCertKR의 각 제품은 무료 데모를 제공합니다. 구입하기로 결정하기 전에 덤프샘플문제로 덤프품질과 실용성을 검증할수 있습니다.