1. John, a team member, will be absent from the team. A new team member, Mary, will take over Johns remaining work. You need to update the project schedule to reflect the change. You also need to retain John's actual work. What should you do?
A) In the Multiple Task Information dialog box, change the resource assignment from John to Mary.
B) In the Resource Usage view, rename John to Mary.
C) In the Assign Resources dialog box, use the Replace feature.
D) In the Resource Sheet view, delete John and add Mary.
2. In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
-Tasks that are not started.
-Tasks in progress.
-Tasks that have finished.
-Total remaining effort for each group of tasks.
What should you do on the View tab?
A) Select Group by Active v. Inactive, and then add the Remaining Work field to the table.
B) Select Group by Complete and Incomplete Tasks, and then add the Work field to the table.
C) Select Group by Active v. Inactive, and then add the Work field to the table.
D) Select Group by Complete and Incomplete Tasks, and then add the Remaining Work field to the table.
3. Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units
and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50
percent on the task. You change John's assignment units to 50 percent for the task.
Which set of values describes the specified task?
A) Duration shows 4 days; Work shows 8 hours
B) Duration shows 2 days; Work shows 0 hours
C) Duration shows 4 days; Work shows 16 hours
D) Duration shows 2 days; Work shows 8 hours
E) Duration shows 2 days; Work shows 16 hours
4. One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
A) The task is late by 14 days.
B) The task is early by 14 days.
C) The task is late by 4 days.
D) The task is early by 4 days.
5. Your customer wants to receive your project's Timeline view in a document by e-mail. You need to create a document that contains only the Timeline view. You select the Timeline view. What should you do next?
A) Select Save View.
B) Select Visual Reports.
C) Select Sync With Task List.
D) Select Create PDF/XPS Document.
질문과 대답:
| 질문 # 1 정답: C | 질문 # 2 정답: D | 질문 # 3 정답: C | 질문 # 4 정답: C | 질문 # 5 정답: B |














896 개 고객 리뷰
품질과 가치ITCertKR 의 높은 정확도를 보장하는 최고품질의 덤프는 IT인증시험에 대비하여 제작된것으로서 높은 적중율을 자랑하고 있습니다.
테스트 및 승인ITCertKR 의 덤프는 모두 엘리트한 전문가들이 실제시험문제를 분석하여 답을 작성한 만큼 시험문제의 적중률은 아주 높습니다.
쉽게 시험패스ITCertKR의 테스트 엔진을 사용하여 시험을 준비한다는것은 첫 번째 시도에서 인증시험 패스성공을 의미합니다.
주문하기전 체험ITCertKR의 각 제품은 무료 데모를 제공합니다. 구입하기로 결정하기 전에 덤프샘플문제로 덤프품질과 실용성을 검증할수 있습니다.